Structural steel construction and floor slab concrete pours are progressing on the upper floors and in the basement level through the month of March.
The large crane onsite is scheduled to be demobilized in early March and will be replaced with a smaller mobile crane to follow for infill steel at the North side of the building.
The man and material hoist on the Southeast side of the building has been installed and will be operational as of the second week of March.
Key upcoming milestones include the commencement of the curtainwall system installation starting at Level 3 in mid-March, which will continue into May and allow for the start of interior framing mechanical system installation later in the spring.